Page 1 of 15

1

CO/2437/2020

HT-2020-000290

IN THE HIGH COURT OF JUSTICE

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

TECHNOLOGY AND CONSTRUCTION COURT (QBD)

AND ADMINISTRATIVE COURT

BETWEEN

THE QUEEN

on the application of

THE GOOD LAW PROJECT

Claimant

-and- MINISTER FOR THE CABINET OFFICE

Defendant

DETAILED GROUNDS OF RESISTANCE

_________________________________________________________________________

INTRODUCTION

1. GLP challenges the decision by the Defendant (“the Authority”) to award a contract to

Public First Limited (“Public First”) for the supply of the following services to assist

the Government in the issuing of emergency messaging to support efforts to combat

Covid-19 (the “Contract”): recruitment and delivery of focus groups and/or mini groups

to an agreed specification, covering the general public and key sub-groups defined by

demographic, life-stage or other agreed criteria; same-day top-line reporting and next- day fuller reporting of focus group findings; and on-site resource to support Number 10

Communications.

2. In its Amended Statement of Facts and Grounds (“SOFG”), the Claimant contends that

the contract award is unlawful and ought to be quashed on three grounds:

(i) Ground 1: The Authority had no basis for making an award of the Contract to

Public First under reg 32 of the Public Contracts Regulations 2015 (“PCR 2015”).

Page 2 of 15

Page 3 of 15

3

effective. It was important to ensure ideas were tested and correct; and not to act on

“hunches” as to what worked. The information gathered from focus groups was therefore

fundamental to the development of Government communication with the general public.

7. There were concerns that the Government’s communications were not as effective as

they could be, and were leading to confusion and concern amongst the public as the first

cases of Covid-19 were confirmed in the UK. There was also concern that PHE did not

have the right resources in place to meet the communications requirements of the

emerging pandemic. They did not have the people or skills needed to undertake this type

of public communications at speed, nor did the DHSC, the NHS or the Cabinet Office.

As a consequence, it was necessary to procure focus group services from external

providers.

8. The seriousness of the pandemic, the importance of effective communications to the

central aim of seeking to protect the public, and thus the urgency with which this work

needed to be progressed were all clear. As noted by Mr Cummings in his statement:

“There is no doubt that the Covid pandemic represented a situation of extreme urgency

where immediate action was required to save lives. Focus groups were a crucial part of

the Governments’ communications strategy...In my opinion it would have been not only

foolish but deeply unethical to delay procurement by even 24 hours given the situation

we faced in February 2020.”

9. On 27 February 2020 Alex Aiken, Executive Director of Government Communication,

Prime Minister’s Office and Cabinet Office Communications, raised with his team the

need for urgent focus group testing of Covid-19 matters, the results of which could be

provided to No. 10 the following day. Mr Aiken was aware that Mr Cummings had

concerns about the approach taken to date; and wanted some research to be done in the

regard ahead of a meeting he had scheduled with Mr Cummings the following day. Helen

Stratton, Head of Insight, Government Communication Service, Prime Minister’s Office

and Cabinet Office, knew that Public First was scheduled to conduct focus groups in

Crawley that evening pursuant to the arrangement detailed in §4 above; and she

recommended using Public First to conduct the Covid-19 focus group research. This was

the only available option which allowed the research to be done that night. Alex Aiken

accepted this recommendation and requested Helen Stratton to take it forwards. Helen

Stratton briefed Public First to change the focus groups in Crawley to Covid-19 research

work that evening and to report the results promptly. Public First provided the results to

No. 10 the next day.

10. At 3pm on 28 February 2020 there was a meeting at No. 10 attended by, inter alia Helen

Stratton, Alex Aiken and Dominic Cummings as well as Gabriel Milland and Person J

from Public First. The key purpose of the meeting was to start work on a very

significantly increased programme of communications to seek to ensure that clear and

effective communications could be used in responding to the pandemic. Representatives

from Public First were asked to attend so that they could provide feedback at the meeting

Page 4 of 15

4

on the research that had been done to date. At this meeting, the decision was made to

carry on with focus groups and to authorise continued research of this kind for all of the

reasons set out above. A steady flow of research to decision makers (including No. 10

and the Chief Medical Officer and Chief Scientific Adviser) was considered essential.

11. It was decided that Public First conduct focus groups the following week, alongside

Britain Thinks. The reasons for that decision were as follows:

(i) There were only two companies in the market that had the scale, expertise and

experience to provide the requisite services in March 2020, being Public First and

Britain Thinks. These were highly specialised services. In contrast, for example,

YouGov and Kantar are primarily quantitative research agencies which do not

specialise in focus groups of the type required to test the sort of government

policy and narrative that was in development.

(ii) Public First were trusted and known to be capable of undertaking these services

speedily and effectively. This was extremely valuable as “in such a high pressure

environment trust is very important”; and as Ms Hunt notes “This was not the

time to take a punt on new agencies.”

(iii) Public First was already in place conducting the research. Using them was the

most efficient and effective way of getting urgently needed research done. It

would have been “utterly impractical” to find another agency to conduct focus

groups for that weekend and the following week.

12. Helen Stratton took this forward in the first instance and met with inter alia Gabriel

Milland from Public First later that day to devise a plan of how the focus groups work

would be carried out over the weekend and the following week. The outline plan

produced was sent to Alex Aiken who, on 29 February 2020, approved the plan for the

initial work. This work was charged at per focus group because Public First had

to recruit participants urgently and could not recruit in the standard manner which

normally took 7 to 10 days. The services provided by Public First were: (i) the

recruitment and delivery of focus groups and/or mini groups to an agreed specification,

covering the general public and key sub-groups defined by demographic, life-stage or

other agreed criteria; and (ii) same-day top-line reporting and next-day fuller reporting

of focus group findings (“focus group services”). (“Same-day top-line reporting” is

providing information on the day of the outcome of the focus groups; “next-day fuller

reporting” is a more detailed report on the outcome of the focus groups.)

13. On 5 March 2020, Public First said that it could provide further focus group services for

the following week, initially at a cost of per focus group and then for later

groups once it had more notice to recruit the focus group participants. Mr Aiken

authorised the use of these further focus Group Services and the additional expenditure

associated with that. The use of focus group services continued to be authorised in a

similar iterative manner as they were needed until more formal arrangements were

ultimately put in place (see §§19 to 23 below).

Page 5 of 15

5

Mr Milland

14. Mr Cummings called Rachel Wolf at Public First to ask if they would allow Gabriel

Milland to work in No. 10 on Covid-19 related matters. He did so on the basis that Mr

Milland had considerable experience of government, and expertise and experience in

communication and research; and that Mr Cummings had worked with Mr Milland

previously and had a high regard of his abilities, expertise and experience. On 16 March

2020, Mr Milland started working in No. 10. Mr Aiken subsequently approved the

reimbursement of Mr Milland’s salary and Mr Milland was engaged through Public First.

He was not employed directly by the Cabinet Office or seconded to them. Mr Milland

ceased to work at No. 10 on 26 June 2020. Thus, he worked for approximately 4 months

at No. 10 to assist with communications at the height of the crisis.

Procurement Processes

15. Reg 32(2)(c) of PCR 2015 was not specifically considered at the time these decisions

were made. However, it was clear to all involved that the conditions for its application

were fulfilled. All those involved were acting rapidly in light of a national emergency in

order to save lives. The information from Covid-19 focus groups was required

immediately, and had to continue to be provided at pace, and with trusted efficiency and

effectiveness, in order to ensure that health messaging in relation to Covid-19 was as

effective as possible. Likewise, the on-site support at No.10 was required as a matter of

urgency. There was no time to conduct even an accelerated procurement exercise for

this work.

16. To place these matters in context the following timeline is indicative:

(i) Wednesday 4 March 2020: DHSC launched a public information campaign on

handwashing. There were 34 recorded cases of Covid-19 in the UK. Italy

announced it was shutting schools and universities.

(ii) Wednesday 11 March 2020: the Chancellor announced a £12bn package of

emergency support to help the UK cope with the expected onslaught from

coronavirus.

(iii) Friday 13 March 2020: widespread cancellation of sporting events including

Premier League football and the London Marathon.

(iv) Monday 16 March 2020: the Prime Minister began daily press briefings and

urged everybody in the UK to work from home and avoid pubs and restaurants to

give the NHS time to cope with the pandemic.

(v) Wednesday 18 March 2020: the Government announced that most schools across

England would shut from Friday 20 March 2020. The Welsh and Scottish

Governments also announced that they will close schools.

Page 6 of 15

6

(vi) Friday 20 March 2020: the Government ordered all pubs, restaurants, gyms and

other social venues across the country to close. The Chancellor announced the

“furlough scheme”.

(vii) Monday 23 March 2020: the Prime Minister, in a televised address to the nation,

asked Britons to “stay at home, protect the NHS and save lives” and only go

outside to buy food, to exercise once a day, or to go to work if they absolutely

cannot work from home.

(viii) Thursday 9 April 2020: the UK recorded its highest Covid-19 daily death toll at

938 deaths.

(ix) Sunday 10 May 2020, Prime Minister announced limited plans for the easing of

lockdown;

(x) Sunday 24 May 2020, it was announced that schools would re-open on a limited

basis from 1 June 2020.

17. In March 2020 most public servants moved to home working. However, this was

impractical for centre of Government communication where co-ordination, rapid

decision making, face to face consultation and the commissioning and sharing of research

and evaluation were critical. A Communications Hub covering media, marketing,

research, behavioural science, digital, evaluation, international and stakeholder

communication work was created in a week going from a staff of 6 to ultimately a staff

of 200. There was no previous model for an operation of this scale. It had to be

constructed quickly to deliver essential public information in the middle of a pandemic.

The Hub served a range of political and official requests and senior staff attended a large

number of meetings across the week. Communications advice, research, evaluation and

marketing plans were needed to support these meetings. These needed to be updated daily

to reflect the developing scenario and advise on public attitudes and the likely response

to the information campaign.

18. There was no time in the critical situation to conduct formal procurements for the services

required. Normal procurement processes took 6-8 weeks in practice. That would have

been entirely impractical in the circumstances. Even an expedited procurement of two

weeks would have taken too long. This was compounded by the difficulty of resourcing

a procurement. Drafting a specification and assessing bids takes time and the team was

already working all available hours, 7 days a week to meet the demands of the crisis.

Formalisation of the Contract

19. In late March 2020 the Cabinet Office, with the assistance of the Crown Commercial

Service (“CCS”), began the process of formalising the arrangements with Public First.

This was a slow process due to the immense pressures on CCS and the Cabinet Office at

that time.

Page 8 of 15

8

the Contract were delivered in March and April; and by May 2020 the work had tailed

off significantly.

Payments made to Public First

25. The sums charged by Public First for the work they undertook were in line with typical

industry costs. Indeed, the Claimant’s own evidence, albeit of limited value given it has

been gathered from unnamed “experienced professionals”, is that a “typical 2-hour

focus group would cost in the region of £5,000” (see First Witness Statement of

, paras 11 and 17). Public First’s charge of per focus group falls well

below that level. Even the higher rate of per focus group, charged in relation to

some of the early focus groups to compensate for the additional costs of recruiting focus

groups on very short notice, falls below the £5,000 average. Thus the sums charged were

not in any way disproportionate and amounted to an entirely fair price.

26. The Contract value was estimated as £840,000 (excluding VAT) to provide flexibility to

procure additional focus groups services as required. This was considered necessary as it

was uncertain what the future demands would be as the pandemic unfolded although it

was recognised that the expenditure could be lower. The sum of £840,000 plus VAT

represented the total possible spend for the contract rather than the actual sum that was

intended to be spent. Under the Contract the following payments were made to Public

First for Covid-19 related work:

Date Payment Work Done

18 March 2020 £58,000 focus groups over

the period 3 March to

15 March 2020 in the

following locations:

London, Manchester,

Bristol, Brighton and

Liverpool.

2 April 2020 £42,000 focus groups over

the period 17 March to

24 March 2020 in the

following locations:

London, Swansea,

Notts/Derby, Watford

and Altrincham.

2 April 2020 £15,000 focus groups over the

period 24 March to 26

March 2020 in the

following locations:

Page 10 of 15

10

reach and BAME

groups) in the following

locations: Nottingham,

Liverpool, Walsall,

Portsmouth, Newcastle,

Glasgow, Norwich,

Aberystwyth,

Manchester from 26

April to 12 June.

(£10,792)

Mr Milland On Site

Resource ( days)

from

(£2395.07)

Mr Milland

Accommodation costs.

9 June 2020 £39,777.23

(£32,500)

focus groups

(including, hard-to- reach and BAME

groups) from 14 May to

28 May 2020.

(£6,248)

Mr Milland On Site

Resource ( days)

over the period

(£1029.23)

Mr Milland

Accommodation costs.

8 July 2020 £78,336.33

(£65,000)

focus groups

(including, hard-to- reach and BAME

groups) from 2 June to

2 July in the following

Page 11 of 15

11

locations: Plymouth,

Newcastle, Manchester,

London, Croydon,

Leeds, Liverpool,

Glasgow, Brighton,

Birmingham,

Nottingham, Leeds,

Manchester, Newbury,

Bradford, Sheffield,

Telford, Norwich,

Plymouth and Hull.

(£11,928)

On Site Resource (

days) over the period

(£1408.33)

Accommodation costs.

14 August 2020 £98,000 (£98,000)

focus groups from 9

July to 27 July in the

following locations:

Bexley, Derby,

Edinburgh, Glasgow,

Bradford, Newcastle,

Plymouth, Great

Yarmouth, Bristol,

South Cambs,

Manchester, Stoke,

Inverness and

Highlands

Total: £564,393.67

27. The payment on 14 August 2020 was for focus groups Public First provided that

were used to research matters relating to the government’s post-coronavirus economic

renewal work and focus groups used to research matters relating to the Union as well

as coronavirus. A payment of £75,000 was made to Public First on 20 March 2020 for

work completed in February and March 2020 but this was unrelated to the Contract.

28. Thus the total sum paid to Public First under the Contract was far below the estimated

Contract value. As can be seen from the foregoing table, there were some delays in

Public First’s invoices being paid in the early stages. This was due to the fact that, at

Page 12 of 15

12

the start of the contract, there was no formal written contract in place which created

internal procedural difficulties in generating the necessary purchase order (“PO”)

numbers required for a payment to be made. The requisite PO numbers were generated

once Person E, HR, Business and Finance Lead, Prime Minister’s Office and Cabinet

Office Communications, was confident that the payment of the sums had been approved

at the requisite level by Alex Aiken.

29. The payments made to Public First on 18 March 2020 and 2 April 2020 were made using

the EU Exit cost centre code because at that time a payment code for Covid-19 related

expenses had not yet been set up. Nonetheless these payments were for Covid-19

research.

GROUND 1: REG 32 OF PCR 2015

30. First, the immediate and continuing provision of the Services was necessary. There were

immediate and the most serious public health risks. Communications and the

development and implementation of the most effective public communications strategy

possible were of paramount and immediate concern. The Services were essential to that

aim. It is clear that the Authority made the direct award for reasons of extreme urgency.

31. Secondly, the pandemic was so novel and fast developing and of such a scale that the

Authority could not have predicted it or the need for the Services to respond to it. The

Authority did not do anything to cause or contribute to the need for extreme urgency.

32. Thirdly, there was no time to run an accelerated procurement under the open or restricted

procedures or competitive procedures with negotiation. There was also no time to place

a call off contract under an existing commercial agreement, such as a framework or

dynamic purchasing system. It is also to be noted that any procurement run at this time

would have had to be conducted on a basis which would comply with the constraints

imposed by the lockdown and social distancing, i.e. a virtual procedure. That mode of

procurement would be wholly unprecedented, was clearly never contemplated by the

legislature when adopting Directive 2012/24/EU and/or the Public Contracts Regulations

2015, and would clearly have substantial implications for the minimum periods within

which any procurement could properly be conducted.

33. Fourthly, other suppliers were not used because they could not provide the requisite

services. Companies like Kantar and YouGov Plc were not viable alternative providers

because they were primarily quantitative research agencies which do not specialise in

focus groups of the type and scale required to test government policy and narrative that

was in development.

34. The conditions for the application of reg 32(2)(c) were thus met. Such an award is also

in accordance with the “Guidance from the European Commission on using the public

procurement framework in the emergency situation related to the COVID-19 crisis” (the

Page 13 of 15

13

“Commission Guidance”). As the Commission Guidance correctly recognises, “for a

situation such as the current COVID-19 crisis which presents an extreme and

unforeseeable urgency, the EU directives do not contain procedural constraints”.

GROUND 2: PROPORTIONALITY OF A SIX-MONTH AWARD

35. The six-month award to Public First was not disproportionate in the unusual

circumstances of this case.

36. First, as noted above, the scale of the national emergency was unprecedented in

peacetime; and the provision of Services was essential to ensure effective

communications of vital health messages to the public.

37. Secondly, the Authority could not risk the Contract expiring before the peak of the crisis

had passed. At the time these matters were determined there was no certainty as to exactly

how the pandemic would unfold or what would be required to fight its impact. There

was, as noted above, discussion about the appropriate length of the Contract. The

decision to make it a six month period was reasonable and proportionate (and indeed the

shortest realistic period) given the anticipated continued need for the Services, their

importance and the considerable uncertainties at the time. So too was the decision to

structure the Contract in summary as a ‘call off’ contract – so that only Services

considered to be necessary from time to time would be called for and paid for.

38. Thirdly, all those involved were having to deal with an immense workload. It would

have been disproportionate to divert their attention and efforts from the critical, and

pressing, to have to conduct a procurement exercise for the Services.

39. In so far as the potential use of the Dynamic Procurement System is concerned, for the

reasons set out in §37 and 63 of Catherine Hunt’s witness statement and 19x of Alex

Aiken’s witness statement, even by using an accelerated process under those

arrangements it would not have been possible to put a contract in place before the end of

March 2020. For the reasons set out above, that would have been far too late for services

which were urgently needed from late February 2020. Moreover, for all the reasons set

out above, the six month award was a proportionate response in the circumstances.

GROUND 3: APPARENT BIAS

40. The test for apparent bias was formulated by Lord Hope (citing Lord Phillips of Worth

Maltravers MR in In re Medicaments and Related Classes of Goods (No 2) [2001] 1

WLR 700) in Porter v Magill [2002] 2 A.C. 357 at 494, §§102-3: “The court must first

ascertain all the circumstances which have a bearing on the suggestion that the [decision

maker] was biased. It must then ask whether those circumstances would lead a fair- minded and informed observer to conclude that there was a real possibility, or a real